Sattva City Project Schedule 2026 Update


Featured Image of Sattva City Project Schedule 2026 Update

Sattva City has received RERA approval (PRM/KA/RERA/1251/472/PR/270226/008494), and construction has started in early 2026. The Project Schedule begins with foundation work in mid-2026. After that, tower construction (21 floors) will take place between 2027 and 2028. Final painting and flooring will be completed by late 2028. During the same time, plumbing, wiring, roads, and power work will also be finished. All amenities and common areas will be ready before the January 2029 possession date so that residents can move in without delay.

Detailed Project Schedule with Construction Timeline for Sattva City


As of 2026, Sattva City is in the main construction stage. The Project Schedule is planned step by step so that the homes are completed and handed over by January 31, 2029. Every stage of work is clearly divided to keep the project moving on time, from foundation work to the final painting and finishing. Below is the simple step-by-step plan showing how this 53-acre township in North Bangalore will be built over the next few years.

Sub-Structure & Foundation Work

The Sub-Structure and Foundation stage is the most important part of the project because it creates a strong base for the entire 53-acre township. During this stage, workers dig the land, level the ground, and build strong footings to support the tall towers. The work also includes basement parking and solid retaining walls to hold the soil in place. All the work happens below the ground, so it takes more time. A strong base ensures the buildings are safe, stable, and ready before construction moves upward.Below is the detailed timeline for these foundational works as per the project schedule plan:

Project Work Estimated Start Date Estimated Completion Date
Earth Work and Other Levelling Preparation Work 01 March 2026 27 April 2027
Foundation Footing Work 01 May 2026 22 September 2027
Up to Plinth Level 01 May 2026 22 September 2027
Sub-Structure Flooring (Parking Floor, etc.) 30 June 2026 14 January 2029
Retaining Wall (All types) 30 June 2026 28 June 2028

Super-Structure: Building the Towers

The Super-Structure phase is the stage where the buildings start rising above the ground. During this time, the shape of the project becomes clearly visible in the North Bangalore skyline. In this stage, workers build the main structure of the towers, including columns, slabs, and walls. All floors of the 21-floor buildings are constructed step by step.Once the basic structure is ready, detailed work begins to turn the concrete frame into comfortable and well-built homes.Below is the timeline for the Super-Structure phase as planned in the project schedule:

Project Work Estimated Start Date Estimated Completion Date
RCC or MS Framed Structure 01 May 202 18 May 2031
Masonry Construction 26 June 2027 02 July 2031
Plastering Inside, Outside & Ceiling 26 July 2027 16 August 2031
Joinery: Doors, Windows, Ventilators, etc. 25 August 2027 31 August 2031
Basic Work of Water Supply, Sanitary and Electrification 11 June 2027 02 July 2031
Dadoing, Skirting, Flooring, Tiles Work (All types) 23 November 2027 30 September 2031
Railing and Grill Fixing 23 December 2027 15 October 2031

Finishing Works & Interior Detailing

The Finishing Works stage is when the building starts to look like a real home. The plain concrete structure is changed into a neat and ready-to-live apartment. In this stage, outside walls are completed, and inside work, like painting, flooring, tiles, doors, and safety fittings, is finished. Every small detail is checked to make sure the home looks good and works properly. All work is completed carefully before the homes are handed over to buyers.Below is the detailed timeline for the finishing and final works as planned in the project schedule:

Project Work Estimated Start Date Estimated Completion Date
Electrification, Water & Sanitary Finishing 18 December 2027 10 October 2031
Painting 22 January 2028 29 December 2031
Fire Prevention & Fitting Network 08 December 2027 13 January 2032
Weather Proof Work (Tile, Concrete) 07 December 2028 20 October 2031
Elevation Work 23 December 2027 29 December 2031
Internal/External Work & Landscapes 17 December 2028 28 February 2032

Internal Infrastructure: Essential Utilities & Wiring

The Internal Infrastructure stage is all about the "hidden" parts of the home that make it run smoothly every day. The project schedule plan includes water pipes, plumbing lines, and main electrical wiring. Basic work on the water supply and basic electrical wiring will start from 11 June 2027 and continue till 02 July 2031. After that, electrical switches and bathroom fittings will be fixed between 18 December 2027 and 10 October 2031. A complete fire safety and firefighting system will be installed from 08 December 2027 to 13 January 2032.

External Infrastructure: Roads, Sewage, and Power

The External Infrastructure stage makes the 53-acre township ready for people to move in. This work includes building roads and footpaths, and setting up the water, drainage, and sewage systems. It also covers the electricity substation, street lights, parks, and tree planting. Systems for recycling waste, saving rainwater, and fire safety are part of this phase as well. All of these landscape and utility works are scheduled to happen from 17 December 2028 to 28 February 2032.

Amenities & Lifestyle Spaces: Clubhouses and Parks

The Amenities and Lifestyle Spaces at Sattva City are planned to give all basic comforts within one big township. The focus is on health, fun, rest, and community life. There will be indoor and outdoor facilities for sports and activities. The 53-acre township will also have open green areas, parks, and common spaces for families to spend time together. All these facilities, including gardens and landscaping, are planned to be ready by 28 February 2032. The table below shows the area planned for the modern amenities.

Project Work Area (Sq Mt)
Parks 39,761.56
Clubhouse 11,740.86
Water and Sanitation 1,830.00
Outdoor Sports facility 1,217.00
Gym 887.00
Community Hall 689.00
Indoor Sports Facility 530.00
Electricity (Infrastructure) 320.00
Swimming Pool 160.00
Power Backup 98.00
Piped Gas 40.00
CCTV Surveillance 9.95

Common Areas & Final Handover

The Common Areas is the final stage of the Sattva City Project Schedule, where the focus is on making the township safe, easy to move around in, and ready to move in. This work includes finishing the massive underground parking, setting up fast elevators, and making sure the grand entrance looks perfect. This phase makes sure fire escapes and security rooms are fully ready. All common areas, along with gardens and parks, will be completed by 28 February 2032. Here is a simple look at the common spaces being built for all residents to use:

Project Work Area (Sq Mt)
Basement (Parking & Utilities) 1,73,664.16
Corridors & Lobbies 39,452.1
Fire Escapes (Safety exits) 18,507.96
Lifts (Elevators) 16,176.96
Staircases 12,394.4
Open Parking Areas 9,926.84
Terrace (Roof areas) 4,249.78
Water & Green Energy Systems 2,405
Main Entrance (Portico/Foyer) 2,033.33
Common Storage Spaces 239.84
Security Staff Lodging 44
Enquiry
Enquire Now