Sattva City Construction Status shows that the project is in the early ongoing stage. It is a large apartment project in North Bangalore. It sits on 53 acres of land in Meenakunte Hosur, Doddajala, Devanahalli, Karnataka. The pre-launch date was December 29, 2024, and the launch date was January 2, 2025. Possession is planned for January 31, 2029. This article will explain the construction status of Sattva City in simple English.
As of June 2025, the construction status of Sattva City is in the early stages. After the launch in January, engineers and workers moved quickly to start site work. Right now, they are finishing the site preparation and laying the foundation. Basic infrastructure work—like roads, water lines, and power lines—has begun. The site looks busy with construction vehicles, machinery, and workers.
The completion time for Sattva City is four years from the launch date. That means full completion by January 2029. The next six months (July 2025 to December 2025) will see structure work for more blocks to reach the 3rd and 4th floors. By mid-2026, builders aim to complete half the tower structures. After that, brickwork, plastering, and flooring will begin on lower floors. Utility work for electricity and water will continue. Landscaping and road paving around the blocks will start in late 2026. By 2027 and 2028, finishing work in apartments and amenities construction will be in full swing. Regular updates on the construction status will help buyers know progress.
The first task after launch was site preparation. Workers cleared the land and removed bushes and debris. They levelled the ground in many areas to make it flat. Surveyors checked the land levels and soil quality. Soil tests were done to make sure the ground was strong enough. Earth-moving machines moved soil to the right spots. Trenches were dug for underground utilities. At this stage, you can still see open patches of land and stacks of steel rods and cement bags.
After site preparation, the team focused on the foundation. Rows of borewells and piles were driven into the ground. This piling work helps support the towers above. Concrete piles are now in place for many blocks. Next, workers started the raft slab for the basement. They poured big sheets of concrete over the piles. This raft slab will hold the weight of the towers. Utility lines for water, sewage, and electricity run under the foundation. You may see pipes and conduits sticking out of the foundation areas. All these steps are part of the “construction status” at this stage.
Structure work has just begun for some blocks. Columns and beams are being cast. For the first few blocks, builders have completed ground-floor columns. Soon, they will work on the first-floor slab. The towers are designed as 2 basements + ground floor + 21 floors. Right now, workers focus on the ground floor and first floor for the earliest blocks. They use formwork to shape concrete slabs. Steel reinforcement bars are tied together before pouring concrete. You can watch cranes lifting steel and concrete buckets as the structure starts to rise.
At this point, internal finishing work is not yet in full swing because the structure is incomplete. However, some test flats or sample areas may be under finishing. These areas allow the builder to show future buyers how flats will look. Sample kitchens, bathrooms, and living rooms are being built with basic fittings. Electrical wiring, plumbing lines, and basic flooring are in test mode in these zones. This is an early part of the construction status that buyers can visit on-site.
Sattva City plans many amenities, such as a clubhouse, swimming pool, sports courts, and landscaped gardens. For now, the space for these amenities is being marked on the site plan. Earthwork is in progress where the clubhouse will stand. Basic drain lines and water lines are laid around the amenity area. Temporary site offices, labour shelters, and material yards are set up. The main entry gate pillars have been built, and temporary security cabins are in place.
The construction status of Sattva City in June 2025 shows that site preparation and foundation work are mostly complete. Structure work is underway for the first blocks, and core amenities are planned on paper. Over the coming years, the project will move from structural work to finishing touches. By January 2029 (possession date), the towers, apartments, and amenities will be ready for families. For now, the site remains active with machines, materials, and hardworking teams focusing on safe and quality construction.